Planning and tracking work

Study Part 8 · Topic 3 of 5

Break the work down, schedule it and track progress so nothing slips.

35 minInteractiveWorking in a project team
0 activities complete
Goals

Make objectives SMART

Flip SMART
SSpecificTap to flipClear and precise: ‘Train 50 admin staff in Excel’.
MMeasurableTap to flipYou can count it: 50 staff, 80% pass rate.
AAchievableTap to flipRealistic with the people and budget you have.
RRelevantTap to flipSupports the organisation’s goals.
TTime-boundTap to flipHas a deadline: by 30 June.
Think first

Make this SMART: ‘Improve our computer skills.’

For example: ‘All 50 administrative staff complete the End User Computing Excel study part with at least 80% by 30 June 2026.’

Breaking it down

Work breakdown structure (WBS)

Build a WBS
1

Start with the deliverable

Staff training launch.

2

Main parts

1. Venue and equipment · 2. Learning material · 3. Learner registration · 4. Training delivery · 5. Evaluation.

3

Tasks

Break each part into tasks of a few days, e.g. 2.1 Update slides, 2.2 Print workbooks, 2.3 Load course on the LMS.

4

Assign and estimate

Give each task an owner, a duration and any dependency (what must finish first).

Schedule

The Gantt chart

A Gantt chart shows each task as a bar on a timeline. The darker part of each bar shows progress; the orange diamond is a milestone (a key checkpoint).

Training launch schedule (8 weeks)
Task
W1W2W3W4W5W6W7W8
Confirm venue & laptopsFacilities
Update learning materialFacilitator
Load course on LMSIT
Register learnersHR
Material readyMilestone
Deliver trainingFacilitator
Evaluate and reportProject manager
Who does what

RACI matrix

Does the work, e.g. the facilitator updates the material.

Owns the result and signs off. Only one person is accountable for each task.

Gives input before the work is done, e.g. the HR manager on learner lists.

Kept up to date, e.g. department heads receive progress reports.

Knowledge check

What does a diamond usually show on a Gantt chart?

Key takeaways

  • Write SMART objectives.
  • A WBS breaks the deliverable into manageable tasks.
  • Gantt charts and RACI show when, who and how far.