Break the work down, schedule it and track progress so nothing slips.
Make this SMART: ‘Improve our computer skills.’
For example: ‘All 50 administrative staff complete the End User Computing Excel study part with at least 80% by 30 June 2026.’
Staff training launch.
1. Venue and equipment · 2. Learning material · 3. Learner registration · 4. Training delivery · 5. Evaluation.
Break each part into tasks of a few days, e.g. 2.1 Update slides, 2.2 Print workbooks, 2.3 Load course on the LMS.
Give each task an owner, a duration and any dependency (what must finish first).
A Gantt chart shows each task as a bar on a timeline. The darker part of each bar shows progress; the orange diamond is a milestone (a key checkpoint).
Does the work, e.g. the facilitator updates the material.
Owns the result and signs off. Only one person is accountable for each task.
Gives input before the work is done, e.g. the HR manager on learner lists.
Kept up to date, e.g. department heads receive progress reports.
What does a diamond usually show on a Gantt chart?